Time and Work: placement practice questions

30 moderate questions in the pattern of campus placement tests. Pick an option to check your answer, then open the step-by-step solution.

Q1Quant · Time and WorkModerate

A can finish a job in 18 days and B in 6 days. In how many days can they finish it working together?

Q2Quant · Time and WorkModerate

A and B together finish a work in 8 days. A alone takes 10 days. How long will B alone take?

Q3Quant · Time and WorkModerate

A can do a work in 30 days and B in 10 days. They work together for 2 days, then A leaves. In how many days in all is the work finished?

Q4Quant · Time and WorkModerate

10 men can finish a job in 12 days. How many days will 6 men take to finish the same job?

Q5Quant · Time and WorkModerate

A is 2 times as efficient as B. Together they finish a work in 24 days. How long would A alone take?

Q6Quant · Time and WorkModerate

A can do a work in 15 days and B in 12 days. They earn Rs. 3600 together for the work. What is A's share?

Q7Quant · Time and WorkModerate

A and B together finish a work in 180/17 days. A alone takes 15 days. How long will B alone take?

Q8Quant · Time and WorkModerate

A can do a work in 20 days and B in 10 days. They work together for 5 days, then A leaves. In how many days in all is the work finished?

Q9Quant · Time and WorkModerate

24 men can finish a job in 12 days. How many days will 9 men take to finish the same job?

Q10Quant · Time and WorkModerate

A is 3 times as efficient as B. Together they finish a work in 11.25 days. How long would A alone take?

Q11Quant · Time and WorkModerate

A can finish a job in 24 days and B in 30 days. In how many days can they finish it working together?

Q12Quant · Time and WorkModerate

A and B together finish a work in 10 days. A alone takes 12 days. How long will B alone take?

Q13Quant · Time and WorkModerate

A can do a work in 15 days and B in 10 days. They work together for 3 days, then A leaves. In how many days in all is the work finished?

Q14Quant · Time and WorkModerate

A is 2 times as efficient as B. Together they finish a work in 12 days. How long would A alone take?

Q15Quant · Time and WorkModerate

A and B together finish a work in 16 4/11 days. A alone takes 30 days. How long will B alone take?

Q16Quant · Time and WorkModerate

A is 2 times as efficient as B. Together they finish a work in 16 days. How long would A alone take?

Q17Quant · Time and WorkModerate

A and B together finish a work in 6 days. A alone takes 10 days. How long will B alone take?

Q18Quant · Time and WorkModerate

A can do a work in 10 days and B in 20 days. They work together for 3 days, then A leaves. In how many days in all is the work finished?

Q19Quant · Time and WorkModerate

24 men can finish a job in 20 days. How many days will 8 men take to finish the same job?

Q20Quant · Time and WorkModerate

A can do a work in 12 days and B in 15 days. They earn Rs. 3600 together for the work. What is A's share?

Q21Quant · Time and WorkModerate

A can do a work in 15 days and B in 12 days. They work together for 5 days, then A leaves. In how many days in all is the work finished?

Q22Quant · Time and WorkModerate

A is 3 times as efficient as B. Together they finish a work in 18 days. How long would A alone take?

Q23Quant · Time and WorkModerate

A can do a work in 8 days and B in 12 days. They earn Rs. 1800 together for the work. What is A's share?

Q24Quant · Time and WorkModerate

A and B together finish a work in 8 4/7 days. A alone takes 15 days. How long will B alone take?

Q25Quant · Time and WorkModerate

A can do a work in 10 days and B in 30 days. They work together for 5 days, then A leaves. In how many days in all is the work finished?

Q26Quant · Time and WorkModerate

A can do a work in 12 days and B in 6 days. They earn Rs. 4500 together for the work. What is A's share?

Q27Quant · Time and WorkModerate

12 men can finish a job in 18 days. How many days will 9 men take to finish the same job?

Q28Quant · Time and WorkModerate

A is 3 times as efficient as B. Together they finish a work in 9 days. How long would A alone take?

Q29Quant · Time and WorkModerate

A can do a work in 12 days and B in 15 days. They earn Rs. 1800 together for the work. What is A's share?

Q30Quant · Time and WorkModerate

A can finish a job in 18 days and B in 30 days. In how many days can they finish it working together?